On May 25, 2023, the Sichuan Cancer Hospital celebrated a significant milestone as the accelerator for the first proton therapy center in the western region was successfully installed. Today, I invite you to explore the latest updates on this project and gain insights into the current situation at the facility.
2023/3/28 / Training for rigging plan
Enhancement of prior management and advance training in large lifting
2023/5 Technical disclosure
Safety technical briefing before accelerator rigging
2023/5 650 ton crawler crane approaching
Installation and initial inspection of 650 ton crawler crane in place
On the day of rigging
On May 25th, a charming 'panda' donning a helmet and safety belt made an appearance at the lifting site to witness the lifting process of the cyclotron at the first proton therapy center in Southwest China.
With the smooth landing of the 'panda', the successful lifting of the proton accelerator is a cause for celebration!
Let's extend our congratulations to Chengdu Cancer Hospital.
The rigging difficulty of this project has set four records since its construction. Firstly, it has the largest lifting radius. Secondly, it has the highest height of the accelerator. Thirdly, it requires the largest tonnage of the crane. Lastly, it has the shortest idle time after the accelerator is put into the site. The successful and smooth lifting operation has earned praise for Better!
The team at Better has been constantly learning from their construction experiences, engaging in discussions with all parties involved, and making continuous improvements. We are grateful for the trust and support of our clients. We remain committed to our initial goals and strive for progress. Our aim is to build our company into a world-class equipment installation company!